Park Street South Retaining Wall

Key details

Current status

Under construction

Location + Section

Northeastern end of Hyde Park South, on Park Street

Type of work

Retaining wall structure maintenance

Start date

27 October 2025

Duration

5 weeks

Work hours

7.30am–5pm Monday to Friday
7.30am–1pm Saturday

Contact

Phillip Britten
Community Liaison Officer
0409 075 591
communityliaison@marineandcivil.com.au

 

Project overview

MCM are undertaking repairs on the stone retaining wall in Hyde Park. This includes the installation of stone indents, coping and pier stones to match the existing structure. Coping stones will be raised and reinstated to the correct alignment. Works also involve mortar repairs to cracked or chipped stones, graffiti removal, full repointing of the wall, low-pressure washing and desalination of all ashlar and piers along the entire length of the wall.

We will work to minimise community impacts during this time, however there will be minor machinery noise during the works.

The safety of everyone is our priority. Thank you for your patience while we complete these important works.

Site location

 
 

Next